Form Traveler-Cantilever Bridge Construction


dnc Uncategorized

The pushing of the form traveler in cantilever bridge construction is a precise and cautious process where a movable scaffolding system is advanced to cast concrete segments incrementally. Key steps include:

  1. Releasing & Adjusting – After a segment is cast and cured, the traveler is carefully moved forward using hydraulic jacks or mechanical systems.
  2. Balanced Advancement – Must be done symmetrically to avoid uneven stresses or deflection.
  3. Alignment Control – Surveying/laser guidance ensures accurate positioning.
  4. Stability Checks – Temporary supports and real-time monitoring prevent deformations.

Precision is critical—misalignment can lead to structural failure. Safety measures and weather considerations are essential during the process.

Vision


To become a proficient Bhutanese engineering firm excelling in the design, construction and Supervision of road and bridges.

Mission


Enhancing Human Resource as a front-driving force to lead and inspire design and construction sectors in Bhutan.

To become full-fledged design and consultation firm by providing quality engineering services.

Set benchmarks by maintaining the highest level of ethical standards in the construction industry

Our services


Through collaboration with internal and external experts, we offer:

Feasibility and Preliminary studies for all types of bridges of various spans,

Design and Construction of various types of bridges,

Design and construction of Road Projects,

Construction Management and Supervision of the Projects.